HARTWOOD VILLAGE – AS OF FEBRUARY 2026
- Mar 12
- 1 min read

HARTWOOD VILLAGE
Percentage Completion:
Land Development: 14.61%
THE FOLLOWING ARE ONGOING WORKS FOR HARTWOOD VILLAGE:
– Ongoing Land development works
Drainage Works
Sewer line Works
Electrical UG Duct line
Auxiliary UG Duct line
Perimeter Fence Construction
– Clubhouse & Bathhouse– Gateway 1 & 2 / Road & Street Lighting
Other lookahead works:
– Road / Street Lighting (Q3 2026)– Clubhouse / Guardhouses & Gates Construction (Q4 2026)– Swimming Pool, Deck, Pumphouse Construction (Q4 2026)– Central Park Site Devt. (Q3 2026)– Landscaping Works / Others (Q3 2026)
License to sell:HLURB LS NO.: DHSUD Region 4A TLS 056 & 072Project Location: Barangay Malamig, Biñan City, LagunaDeveloper: Horizon Land Property Development CorpOwner: Horizon Land Property Development CorpCompletion Date: June 2026 (Phase 1) January 2027 (Phase 2)